Codify — Article

California SB 886: Tariffs and obligations for data center interconnections and large loads

Requires the CPUC to create electrical‑corporation tariffs that allocate interconnection and resource costs to large new loads—targeting data centers—to protect other ratepayers and require onsite clean resources and storage.

The Brief

SB 886 directs the California Public Utilities Commission to establish or modify an electrical‑corporation tariff by July 1, 2027 that governs interconnection and provision of generation, transmission, and distribution service for ‘‘participating customers’’—primarily large data centers and other large load facilities. The bill assigns explicit cost responsibility to participating customers for transmission upgrades, requires prefunding of long‑term zero‑carbon resources, mandates onsite energy storage and demand response participation, and creates refund and early‑termination rules tied to actual revenues.

The statute aims to prevent cost‑shifting to nonparticipating ratepayers while forcing large new loads to internalize grid impacts. That changes the economics of siting and operating large data centers in California, affects procurement choices by community choice aggregators and electric service providers, and raises implementation questions about federal interconnection rules and how utilities will operationalize dispatchable onsite assets and refund calculations.

At a Glance

What It Does

The bill requires the CPUC to adopt an electrical‑corporation tariff covering interconnection and service to participating customers, with eligibility criteria, interconnection cost allocation, and requirements that participating customers prefund long‑term zero‑carbon resources and install dispatchable onsite storage. It also imposes demand response participation, an annual refund cap tied to net revenues, and an early termination fee for premature departures or failure to ramp.

Who It Affects

Primary targets are data centers and other facilities taking transmission‑level service (definitions in the bill set 25 MW and 75 MW thresholds for various purposes), investor‑owned electrical corporations subject to CPUC jurisdiction, community choice aggregators and electric service providers asked to accept prefunded contracts, and nonparticipating ratepayers the bill seeks to protect. Local publicly owned utilities are only encouraged, not required, to adopt similar tariffs.

Why It Matters

SB 886 shifts more upfront capital and long‑term procurement obligations onto large new loads, which changes project financing and contracting strategies and may alter siting decisions. At the same time, it attempts to lock new load growth into meeting California’s reliability and decarbonization goals while limiting the risk that incumbent ratepayers absorb new infrastructure costs.

More articles like this one.

A weekly email with all the latest developments on this topic.

Unsubscribe anytime.

What This Bill Actually Does

SB 886 starts by defining the players: ‘‘participating customers’’ are customers receiving service under the new tariff, with a special interconnection definition that targets data centers taking transmission‑level service at an estimated peak of at least 25 megawatts. The bill also defines ‘‘large load customer’’ for other purposes as facilities with estimated peak demand of at least 75 megawatts and excludes some customers that add load by electrifying from fossil fuels.

These definitions set who will face the bill’s new obligations.

The core mandate requires the California Public Utilities Commission to create—or modify—an electrical‑corporation tariff that addresses interconnection, and the allocation of generation, transmission, and distribution costs for participating customers. The tariff must include eligibility rules, an assessment of risks to nonparticipating customers, and explicit protections against stranded costs or cost shifts.

For unbundled customers (those who buy generation from a different provider), the tariff must separate generation charges from transmission and distribution charges.On resource obligations, the bill forces participating customers to prefund a minimum 15‑year contract for new, incremental, zero‑carbon resources that will supply at least half of their hourly energy needs and provide dispatchable reliability assets inside the utility’s service territory; as an alternative, customers may install equivalent zero‑emission onsite resources behind the meter. The bill also requires participating customers to install onsite zero‑carbon storage sized to deliver at least four hours of capacity equal to half of forecasted peak demand, and to participate in commission‑authorized demand response programs, including via third‑party aggregators.

The storage must be dispatchable by the electrical corporation or the Independent System Operator for emergency grid conditions.For interconnection mechanics, SB 886 assigns cost responsibility for transmission upgrades triggered by a new interconnection to the participating customer, including shared network upgrades to the extent federal law allows. It requires disclosure when the same project has interconnection applications in other territories, caps annual refunds to participating customers at no more than 75 percent of the electrical corporation’s annual net revenues from that customer, and imposes an early termination fee if a participating customer leaves the system or fails to reach its forecasted load within 15 years—the fee set at no less than the revenue gap tied to the originally projected demand and energy consumption.

Investor‑owned utilities must also publish maps identifying locations where large loads can interconnect without major transmission upgrades. Local public utilities are encouraged, but not required, to adopt comparable tariffs and to prevent cost shifting within their service territories.

The Five Things You Need to Know

1

The CPUC must establish or modify the tariff by July 1, 2027; the interconnection rules only apply to facilities with new transmission interconnection agreements established after the tariff’s adoption (or a later date the CPUC sets).

2

For interconnection purposes the bill targets data centers taking transmission‑level service with an estimated peak demand of at least 25 megawatts; the commission may set a separate minimum for other tariff components but not higher than 25 MW.

3

Participating customers must prefund a minimum 15‑year contract for new, incremental zero‑carbon resources that supply at least 50% of hourly energy needs and provide dispatchable reliability assets within the service territory; onsite zero‑emission alternatives are allowed.

4

Each participating customer must install onsite zero‑carbon energy storage with at least four hours of capacity sized to no less than 50% of forecasted peak demand; the utility or CAISO must be able to dispatch it during emergencies.

5

Transmission upgrades triggered by interconnection are assigned to the participating customer, who may receive refunds capped at 75% of the utility’s annual net revenue from that customer; leaving or failing to ramp within 15 years triggers an early termination fee at least equal to the projected revenue gap.

Section-by-Section Breakdown

Every bill we cover gets an analysis of its key sections. Expand all ↓

Section 8541

Definitions and scope

This section pins down the key terms that determine who the tariff will cover: data center, large load customer, participating customer, nonparticipating customer, unbundled customer, and facility. Practically, those definitions decide whether a project faces the tariff’s obligations or remains outside CPUC jurisdiction (or only subject to encouragement for local publicly owned utilities). The dual thresholds—25 MW for interconnection-defined participating customers and 75 MW for ‘‘large load customer’’ elsewhere—create different treatment tracks for projects of varying sizes.

Section 8542(a)

CPUC deadline and rulemaking vehicle

The CPUC must adopt the tariff by July 1, 2027, either through a general rulemaking or an electrical‑corporation specific application. That gives the commission latitude to tailor rules to individual utilities or to issue a uniform policy, but it also raises the prospect of staggered, utility‑specific implementation schedules depending on the chosen vehicle.

Section 8542(b)–(c)(1–2)

Eligibility, evaluation, and charge separation

The CPUC must set eligibility criteria and evaluate risks to nonparticipating customers while ensuring the tariff prevents stranded costs and cost‑shifting. For customers with unbundled service, the tariff requires that generation charges be separately identified from transmission and distribution charges, which affects billing system design and cost allocation in multi‑provider arrangements.

4 more sections
Section 8542(c)(3)

Prefunding zero‑carbon resources and onsite option

The tariff requires participating customers to prefund at least 15‑year contracts for new, incremental, zero‑carbon energy resources that meet two tests: supply at least 50% of the customer’s hourly needs and deliver dispatchable reliability assets inside the service territory. The practical implication is that developers must negotiate long‑term supply deals with an electrical corporation, CCA, or ESP or invest in equivalent onsite zero‑emission assets, changing how projects are financed and how CCAs/ESPs plan long‑term resource portfolios.

Section 8542(c)(3)(5) (interconnection provisions)

Interconnection disclosures, cost responsibility, refunds, and early‑termination fee

Interconnection applicants must disclose parallel interconnection filings in other jurisdictions, which aims to prevent serial or speculative queue filings. The bill assigns transmission upgrade costs to participating customers, including shared network upgrades as federal law allows, and allows limited refunds of initial interconnection contributions—capped at 75% of annual net revenues—thereby stretching the recovery timeline for participating customers. The early termination fee, set at not less than the revenue gap over the 15‑year projection, creates a financial deterrent to abandoning a project or under‑constructing it relative to forecasts.

Section 8542(c)(4)–(6), (d), (e)

Onsite storage, demand response, certification, and interconnection maps

The bill requires onsite zero‑carbon storage sized to four hours at no less than half of forecasted peak demand and makes that storage dispatchable by the utility or CAISO for emergencies. It mandates participation in existing commission demand response programs and requires utilities to publish maps showing where large loads can interconnect without major transmission upgrades—tools meant to reduce siting surprises and speed planning, but which also impose new technical and contractual requirements on developers and utilities alike.

Section 8543

Local publicly owned utilities encouraged to adopt similar tariffs

Rather than imposing the tariff on publicly owned utilities, the bill encourages them to adopt similar rules that prevent intra‑utility cost‑shifting and prohibit recovery of a large load’s infrastructure investments from other nonparticipating customers. It requires certifications that facilities meet certain Public Resources Code standards, signaling the Legislature’s intent while leaving final design and enforcement to local agency discretion.

At scale

This bill is one of many.

Codify tracks hundreds of bills on Energy across all five countries.

Explore Energy in Codify Search →

Who Benefits and Who Bears the Cost

Every bill creates winners and losers. Here's who stands to gain and who bears the cost.

Who Benefits

  • Nonparticipating ratepayers: The bill is designed to stop new large loads from shifting the costs of transmission upgrades and other societal obligations onto existing distribution‑level customers, protecting their bills from being increased by new, costly interconnections.
  • Renewable and storage project developers: Prefunding requirements and 15‑year contracts create a stable revenue stream and signal demand for new, incremental zero‑carbon resources, improving bankability for developers willing to serve large loads.
  • Grid operators and reliability planners (CAISO, utilities): Onsite dispatchable resources and mandatory demand response participation increase local flexibility and resource adequacy options during emergencies, providing tools to manage rapid load swings from large facilities.
  • Community Choice Aggregators and Electric Service Providers: CCAs/ESPs that accept prefunded long‑term contracts gain new market opportunities to provide or broker zero‑carbon resources to large industrial customers.
  • Local communities concerned about siting surprises: Required interconnection maps give communities earlier clarity on where projects are less likely to trigger major transmission expansions.

Who Bears the Cost

  • Participating customers (data centers and other large loads): They face direct costs for transmission upgrades, long‑term prefunding of zero‑carbon resources, onsite storage procurement and installation, demand response participation, and potential early termination fees.
  • Investor‑owned utilities (electrical corporations): Utilities must implement new tariffs, publish interconnection maps, administer refund calculations and dispatchable controls for customer‑owned assets, and absorb administrative and planning costs associated with the new regime.
  • Community Choice Aggregators and Electric Service Providers: CCAs and ESPs asked to enter or administer 15‑year contracts may face procurement, financing, and portfolio‑risk management costs tied to serving a single large customer.
  • Project developers and investors: The increased upfront obligations and revenue‑risk protections (refund caps, early termination fees) complicate project financing and could raise the cost of capital or discourage projects that cannot meet the bill’s resource and storage thresholds.

Key Issues

The Core Tension

The bill forces a trade‑off between two legitimate aims: protecting existing ratepayers and the grid from expensive, anticipatory upgrades caused by rapid industrial load growth, and keeping California competitive for large data center investment. Meeting both goals demands imposing heavy upfront costs and operational constraints on new loads, which reduces cost‑shift risk but may deter investment or reroute projects to jurisdictions with lighter requirements—there is no mechanism in the bill that fully resolves that balancing act.

SB 886 creates a state‑level framework that runs into federal jurisdictional limits. Assigning cost responsibility for shared transmission network upgrades ‘‘to the extent permitted under federal law’’ punts on how much of the federal interconnection and regional transmission cost allocation regime the CPUC can override—practical outcomes will depend on FERC precedent and CAISO rules.

That uncertainty affects both the size of prospective interconnection bills and the willingness of developers to accept them.

The bill’s prefunding and onsite resource requirements are blunt tools to internalize grid costs, but implementing them raises measurement and control challenges. How will the CPUC verify that contracted resources deliver 50% of hourly needs?

What metrics and enforcement mechanisms will ensure onsite storage is truly dispatchable by the utility or CAISO during emergencies? The refund cap tied to ‘‘annual net revenues’’ demands a robust, auditable definition of net revenue and a transparent accounting methodology; otherwise the refund regime will generate disputes and litigation.

Finally, the combination of large upfront obligations and the risk of a multi‑year revenue gap recovery via early termination fees may push some projects to other states rather than reform siting practices within California.

Try it yourself.

Ask a question in plain English, or pick a topic below. Results in seconds.