Codify — Article

Bill blocks interstate cost-allocation for transmission projects tied to another State’s policy

Shifts bargaining power over who pays for multi‑state grid projects to state governments by banning allocations to non‑consenting States unless a public official expressly agrees.

The Brief

The Fair Allocation of Interstate Rates Act adds a new prohibition to the Federal Power Act that stops transmission providers from allocating costs for interstate transmission projects when those projects were planned or built to implement a specific State’s policy, if the consumers being asked to pay did not belong to that State and the State of those consumers did not expressly consent. The bill preserves a narrow exception: cost allocation is allowed only where the consumer’s State or a designated public official of that State expressly agrees to the allocation.

The change would alter the default for regional cost‑sharing. By making express state consent the gatekeeper for cross‑state cost allocation and by prescribing statutory presumptions about which consumers are “cost causers,” the bill could complicate multi‑state planning, financing, and tariff filings handled by RTOs/ISOs and FERC — particularly for projects tied to state-driven clean‑energy policies.

It pushes a dispute over allocation from tariff and regional planning processes into state legislatures and executive offices, with operational and legal consequences for developers, utilities, and ratepayers.

At a Glance

What It Does

The bill amends the Federal Power Act to forbid allocating the costs of a transmission facility to consumers outside the State whose policy motivated the project, unless the outside consumer’s State or a designated public official expressly consents. It also creates statutory presumptions about who benefits and who counts as a cost causer.

Who It Affects

Transmission providers operating across multiple States, RTOs/ISOs that propose regional cost‑allocation formulas, project developers seeking to finance long‑distance lines, state public officials who may be asked to grant or withhold consent, and ratepayers in both policy and non‑policy States.

Why It Matters

The bill changes how interstate transmission costs get negotiated and approved: instead of being worked out in regional planning and tariff proceedings, cost allocation can hinge on state-level consent. That raises the cost and political friction of multi‑state projects — especially those built to advance one State’s clean-energy objectives.

More articles like this one.

A weekly email with all the latest developments on this topic.

Unsubscribe anytime.

What This Bill Actually Does

The bill inserts a new subsection into Section 205 of the Federal Power Act that places a statutory bar on allocating the costs of certain interstate transmission facilities to consumers who live outside the State whose policy is the stated basis for the project. It applies when a transmission provider serves customers in two or more States.

The bar is absolute unless the consumer’s State, or a designated public official of that State, gives express consent to the allocation.

The statute defines two key phrases. A "covered policy" is any State policy, including those adopted by local political subdivisions.

A "covered transmission facility" is any interstate transmission line, facility, equipment, or system planned, constructed, or operated in whole or in part to implement such a covered policy. The bill also spells out three presumptions: that the benefits of such a facility accrue solely to the cost causers; that only consumers in the State that enacted the covered policy are cost causers; and that consumers outside that State are not cost causers.

Those presumptions operate as a starting legal posture that proponents of allocation will need to overcome when seeking to spread costs beyond the policy State.Practically speaking, the bill redirects a central fact question — whether a project was planned or built, in whole or in part, to implement a State policy — into regulatory and potentially judicial disputes. Under current regional models, RTO/ISO planning bodies and FERC resolve cost‑allocation proposals through technical studies, stakeholder processes, and tariff filings.

This bill makes state consent an independent statutory requirement for allocation when projects are motivated by state policy, which will require proponents to secure intergovernmental agreements or formal state resolutions before asking FERC to approve regional cost sharing.The bill also forces FERC into a short implementation timetable: it directs the Commission to issue rules and regulations within six months of enactment to implement the new subsection. In operation that means FERC must decide how to interpret "basis...to implement a covered policy," define what constitutes "express consent" and a "designated public official," and determine how the statutory presumptions interact with evidentiary burdens in allocation proceedings.

Those interpretive choices will have large practical effects on whether cross‑state projects proceed, how they are financed, and who ultimately bears the cost.

The Five Things You Need to Know

1

The bill amends Section 205 of the Federal Power Act by inserting a new subsection that restricts interstate cost allocation for certain transmission facilities.

2

It applies only to transmission providers that serve consumers in two or more States — single‑State providers are outside the prohibition.

3

The statute creates a rebuttable legal presumption that benefits from a covered transmission facility accrue solely to the consumers in the State whose policy motivated the project (i.e.

4

the presumptive ‘cost causers’).

5

A transmission provider may allocate costs to consumers outside the policy State only if that consumers’ State, or a designated public official of that State, provides express consent to the allocation.

6

The bill requires the Federal Energy Regulatory Commission to issue rules and regulations necessary to implement the new subsection within six months of enactment.

Section-by-Section Breakdown

Every bill we cover gets an analysis of its key sections. Expand all ↓

Section 1

Short title

Establishes the Act’s short title as the "Fair Allocation of Interstate Rates Act." This is a technical provision but signals the bill’s intent to govern interstate rate allocation rather than transmission siting or reliability standards.

Section 2 — Amendment to 16 U.S.C. 824d (new subsection (h))

Prohibition on cross‑state cost allocation tied to another State’s policy

Adds the core rule: a transmission provider serving customers in two or more States cannot allocate costs for a "covered transmission facility" to customers who are not residents of the State whose policy motivated the project. That prohibition is categorical unless an exception applies. For practitioners, this injects a statutory bar into the rate‑setting section of the Federal Power Act — the same provision that authorizes FERC to regulate wholesale rates — meaning allocation arguments now must clear both tariff and statutory hurdles.

Section 2(2) — Exception

Express consent by the consumer’s State

Creates a narrowly drawn exception: cost allocation to an out‑of‑State consumer is lawful only where the consumer’s State, or a public official the State designates, expressly consents. The bill does not specify the form or process for that consent, leaving FERC to define whether a legislative resolution, governor’s letter, utility commission action, or some other mechanism qualifies. That omission will be a central focus of the required FERC rulemaking.

2 more sections
Section 2(3) — Presumptions about benefits and cost causers

Statutory presumptions that favor policy State ratepayers

Establishes three presumptions: (A) benefits of a covered facility accrue solely to cost causers; (B) only consumers in the policy State are cost causers; and (C) consumers outside that State are not cost causers. In practice, these presumptions shift the initial evidentiary posture: proponents seeking allocation beyond the policy State will face an uphill task rebutting a default legal presumption that out‑of‑State consumers should not pay.

Section 2(4)–(5) — Implementation and definitions

FERC rulemaking deadline and key definitions

Directs FERC to promulgate implementing rules within six months and supplies working definitions for ‘‘covered policy’’ (explicitly including local political entities) and ‘‘covered transmission facility’’ (interstate transmission planned, constructed, or operated to implement a covered policy). The short deadline forces FERC to prioritize interpretive questions — for example, how to determine partial motivation — and to set procedural requirements for recognizing state consent.

At scale

This bill is one of many.

Codify tracks hundreds of bills on Energy across all five countries.

Explore Energy in Codify Search →

Who Benefits and Who Bears the Cost

Every bill creates winners and losers. Here's who stands to gain and who bears the cost.

Who Benefits

  • Ratepayers in States that did not adopt the motivating policy — the bill blocks automatic allocation of costs to them for projects built primarily to carry out another State’s policy, protecting those consumers from paying for externally motivated projects without their State’s approval.
  • State governments and public officials who oppose out‑of‑State cost impositions — the statute gives legislatures and governors clear leverage to accept or reject cost allocation for projects that serve other States’ policy goals.
  • Local governments and municipalities that adopt policies — by defining 'covered policy' to include local political entities, the bill gives local policy choices a stronger claim to keep costs local and to solicit funding only from consenting jurisdictions.

Who Bears the Cost

  • Transmission developers and investors — the new statutory hurdle raises allocation risk, increasing financing costs for multi‑state projects and possibly shrinking the pool of bankable projects.
  • Consumers and utilities in the policy State — if out‑of‑State allocation is blocked or consent withheld, the policy State’s ratepayers (or taxpayer backstops) may have to shoulder a larger share of project costs or see projects delayed or canceled.
  • RTOs/ISOs and FERC — the Commission and regional planners must manage new evidentiary and procedural questions, run contentious stakeholder processes, and litigate disputes over factual motivation and the form of state consent.
  • Clean‑energy project proponents that rely on long‑distance transmission — projects built to interconnect renewables in one State for use in another may become harder to cost‑share across State lines, potentially slowing decarbonization investments.

Key Issues

The Core Tension

The bill resolves one fairness problem — preventing consumers from being forced to pay for another State’s policy — by increasing frictions around building and financing interstate infrastructure; it forces a trade‑off between protecting State sovereignty and ratepayer consent on the one hand, and preserving the efficient, regional planning and cost‑sharing needed for reliability and decarbonization on the other.

The bill raises immediate implementation questions that have no mechanical, uncontested answers. First, the critical statutory hook — whether a transmission facility was planned, constructed, or operated "in whole or in part to implement a covered policy" — demands a fact‑intensive inquiry into motives, planning documents, and engineering studies.

Proponents will argue projects have multiple purposes (reliability, congestion relief, access to generation) while opponents will identify policy‑driven language in solicitation or routing decisions. FERC will need to develop standards of proof and procedures for parsing mixed motivations; how it does so will largely determine whether the statute is a modest restraint or a practical veto.

Second, the bill’s silence about what counts as "express consent" and who qualifies as a "designated public official" creates more political and legal ambiguity than clarity. If FERC requires a legislative act or statewide regulatory finding, consent will be hard to obtain quickly; if a governor’s letter suffices, consent becomes politicized and potentially reversible.

The decision shapes power dynamics — making consent formal and hard raises barriers to allocation; making it easy risks lipstick on a pig where perfunctory approvals merely enable cost shifting.

Third, the statutory presumptions shift the evidentiary burden but do not eliminate disputes over measurement of benefits. RTO technical models quantify network benefits and beneficiary shares; courts and FERC will have to reconcile those methods with the new presumptions.

Finally, the bill can produce perverse incentives: policy States may be forced to internalize costs (raising local rates) or seek legislative carve‑outs, while non‑consenting States can free‑ride on regional reliability investments. Those trade‑offs are not hypotheticals — they are practical constraints that will shape whether multi‑state transmission planning survives in its current form or fractures into more bilateral, contract‑based arrangements.

Try it yourself.

Ask a question in plain English, or pick a topic below. Results in seconds.