Bill 5 is a wide-ranging omnibus law that repackages procurement policy, resource approvals and environmental law into a single Act. It adds origin-based procurement restrictions for the IESO, Ontario Power Generation and regulated energy licensees; creates ministerial powers to suspend or restrict mining-administration functions, cancel claims and fast-track permitting through ministerial delivery teams; and enacts a new Special Economic Zones Act that lets the provincial cabinet exempt designated projects or proponents from statutory and local rules.

The bill also repeals and replaces the Endangered Species Act with a new Species Conservation Act that replaces some automatic protections with a registry-and-permit regime, expands inspection and enforcement powers across heritage and species law, and contains multiple extinguishment provisions that bar most private legal claims connected to the new measures. The package is significant because it substitutes discretionary executive tools and regulatory exemptions for long-standing procedural safeguards and creates new axes of regulatory uncertainty for suppliers, municipalities, resource proponents and Indigenous and conservation stakeholders.

At a Glance

What It Does

The Act authorizes (1) origin-based procurement limits for electricity, gas and licensees that regulators or cabinet later prescribe; (2) ministerial orders to suspend mining-system functions for short periods, to block registrations and to cancel or terminate claims or licences without compensation; and (3) creation of special economic zones where the Lieutenant Governor in Council can exempt trusted proponents or projects from other Acts and municipal bylaws.

Who It Affects

Directly affected parties include the IESO, Ontario Power Generation and regulated gas/energy licensees; mining proponents and users of the provincial mining lands administration system; proponents designated for accelerated permitting; municipalities faced with potential by-law exemptions in special economic zones; suppliers subject to 'origin' rules; and parties and NGOs who previously relied on statutory remedies under environmental and heritage regimes.

Why It Matters

The bill shifts discretion from statutorily prescriptive processes to ministerial and cabinet rule‑making and orders, and erects statutory barriers to private litigation. That combination changes how compliance risk, procurement decisions and project timelines are managed in Ontario — it privileges speed and supply‑chain control but raises questions about accountability, Indigenous consultation, judicial oversight and compatibility with trade and procurement obligations.

More articles like this one.

A weekly email with all the latest developments on this topic.

Unsubscribe anytime.

What This Bill Actually Does

Bill 5 is an omnibus statute that retools procurement, resource approvals and several environmental and heritage regimes into a provincially driven, discretionary framework. For energy procurement, the IESO and Ontario Power Generation (and later other regulated licensees) must follow any restrictions the regulations or directives set about the country, region or territory of origin of goods, services or beneficial owners; the bill makes the Discriminatory Business Practices Act inapplicable to actions taken under those directives or regulations.

The bill says those procurement restrictions apply only for procurements where the final RFP or contract has not yet been issued or executed when the relevant regulation comes into force, so the restriction is prospective, not retroactive.

In mining, the Minister gains short‑term emergency-like powers: the mining lands administration system can be partly suspended without prior notice or hearing (orders last 10 days unless extended), accounts can be suspended or terminated, people can be blocked from registering or obtaining prospector licences, and the Minister (with LGIC approval in some cases) may cancel unpatented claims or terminate leases. The Act also establishes a ministerial “mine authorization and permitting delivery team” for designated projects that must prepare an integrated authorizations plan if the proponent supplies prescribed information; regulations may set service standards and limited refund rules tied to fees paid.The bill removes the Endangered Species Act and enacts the Species Conservation Act.

COSSARO (the species committee) continues to assess and classify species, but cabinet listing becomes discretionary: the Lieutenant Governor in Council may make the Protected Species list and is not required to list all species COSSARO classifies. The new Act establishes a Species Conservation Registry, turns many activities into registration or permit activities, replaces some prior instruments with permits and expands provincial officer inspection, contravention and mitigation orders.

It also sets up a new appeal path to the Ontario Land Tribunal; initiating an appeal does not automatically stay orders or permits unless the Tribunal grants a stay.Across multiple Schedules the government inserted broad extinguishment clauses: most private causes of action, claims for damages and remedies in connection with actions taken under the new procurement, mining, SEZ or heritage provisions are barred, except for applications for judicial review or constitutional remedies. The Heritage Act and related schedules broaden inspection powers, permit ministerial assessment orders that freeze alteration until archaeological fieldwork is completed, and create investigator powers, production orders and short limitation periods for provincial offences in specified contexts.

Environmental Assessment changes include terminating the Eagle’s Nest agreement and revoking its approval and exempting specified activities at the Chatham‑Kent waste disposal site from Part II.3 review. Finally, the Special Economic Zones Act allows cabinet to designate zones, trusted proponents and designated projects and to exempt or modify how provincial statutes and municipal bylaws apply to them.

The Five Things You Need to Know

1

Procurement origin rules are prospective: they bind IESO/OPG/licensees only where regulations begin to apply before the final RFP is issued or before the parties enter a final contract.

2

The Mining Act gives the Minister power to suspend mining‑system functions without prior notice for up to 10 days (extendable) and to suspend or terminate user accounts, block registrations, deny prospector licences and—subject to LGIC approval—cancel unpatented claims or terminate leases with no compensation.

3

The Species Conservation Act removes the automatic temporary suspension on first listing, creates a Species Conservation Registry and makes many formerly prohibited activities lawful only if registered or carried out under a ministerial permit, shifting the compliance model to registration/permits.

4

Multiple new extinguishment clauses bar most private civil, contractual or arbitral claims arising from acts taken under the new measures, while preserving only judicial review and constitutional remedy routes; awards and enforcement outside Ontario are also targeted by the bars.

5

The Special Economic Zones Act authorizes LGIC regulations that can exempt trusted proponents or designated projects from other Acts, regulations and municipal by‑laws, and to modify statutory application for projects in designated zones.

Section-by-Section Breakdown

Every bill we cover gets an analysis of its key sections. Expand all ↓

Schedule 1 (Electricity Act, 1998)

Origin-based procurement rules for IESO and legal immunity

▾

This schedule lets directives to the IESO include requirements or restrictions about the country, region or territory of origin of goods, services or participants, and gives cabinet power to prescribe when the IESO may not enter a procurement contract on those grounds. It adds a narrow non-retroactivity trigger tied to the issuance of an RFP or final contract and also creates an extinguishment provision that bars most private remedies against Crown actors, IESO officials and OPG personnel for actions taken under the procurement restrictions (judicial review and constitutional claims remain). Practically, procurement teams will need to watch when any new regulations come into force because the rules only apply to procurements that are still at the solicitation or pre-contract stage.

Schedule 5 (Mining Act)

Ministerial suspension and claim‑cancellation powers; permitting delivery teams

▾

The Mining Act amendments create rapid, extra‑procedural tools for the Minister to protect what the bill calls the 'strategic national mineral supply chain.' The Minister may suspend parts of the mining lands administration system without notice (10‑day default duration, extendable), issue orders suspending user accounts, blocking registrations or terminating licences, and—subject to LGIC approval—cancel unpatented claims or terminate leases without compensation. The Act also authorizes mine authorization and permitting delivery teams: if a proponent supplies prescribed information the team must prepare an integrated authorization plan and coordinate ministries; regulations can set service standards and limited fee‑refund mechanics. These powers prioritize rapid government control over mining access and administrative gating, while explicitly removing judicial remedies in many contexts.

Schedule 9 (Special Economic Zones Act, 2025)

Designated zones, trusted proponents and statutory exemptions

▾

The new Special Economic Zones Act empowers the Lieutenant Governor in Council and the Minister to designate geographic zones, trusted proponents and projects. Regulations may exempt those proponents or projects from the application of provincial Acts, regulations and other instruments — explicitly including municipal by‑laws — or to modify how those instruments apply. The Act also contains an extinguishment clause that prevents most private legal actions connected to designations or regulation changes. For municipal lawyers and planners this creates a pathway for provincial override of local controls on designated developments.

4 more sections▾
Schedule 10 (Species Conservation Act, 2025)

Replacement of the Endangered Species Act with a registry-and-permit model

▾

This Schedule repeals the Endangered Species Act and enacts the Species Conservation Act. It preserves COSSARO but makes cabinet listing discretionary: cabinet may make a Protected Species regulation and is not required to list every species COSSARO classifies. The new regime establishes a Species Conservation Registry, requires registration for many activities and makes some activities legal only under ministerial permits. The Minister has expanded powers to issue mitigation, habitat protection, species protection and contravention orders; provincial officers get broader inspection and inquiry powers; and appeals go to the Ontario Land Tribunal, where commencement of a Tribunal hearing does not automatically stay the underlying permit or order. The schedule also winds up the previous Agency, moves account balances into a Species Conservation Account and contains transitional rules.

Schedule 7 (Ontario Heritage Act)

Expanded archaeological inspections, assessment orders and investigators

▾

Amendments expand inspector powers to assess for archaeological sites on land or under water (ministerial direction required), authorize ministerial assessment orders that freeze alteration until licensed archaeological fieldwork and reporting are complete, authorize seizure and deposit of artifacts (including deposit with Indigenous communities), and create a new Part VI.1 to appoint investigators with warrant, production‑order and exigent‑circumstance search powers. The Schedule also creates an exemption mechanism (LGIC orders) to exempt property from Part VI requirements if doing so advances specified provincial priorities (transit, housing, health, infrastructure).

Schedule 3 (Environmental Assessment Act)

Eagle’s Nest termination and targeted Part II.3 exemptions

▾

The Environmental Assessment Act amendments terminate the 2011 Eagle’s Nest Agreement and revoke the related 2015 approval, and they exempt specified Chatham‑Kent waste‑disposal activities from the Part II.3 process. These are narrow, project‑specific changes that remove existing EA instruments and carve out certain projects from Part II.3 review; the measures are enacted in the text rather than left entirely to subsequent regulation.

Schedule 6 (Ontario Energy Board Act, 1998)

Procurement restrictions for gas transmitters, licensees and immunity

▾

Parallel to the electricity schedule, the Ontario Energy Board Act now authorizes regulations that bar gas transmitters, distributors, storage companies and other licensees (and prescribed subsidiaries) from procuring goods or services that meet prescribed origin conditions, with the same prospective trigger tied to RFP/contract timing. It also adds a statutory extinguishment of causes of action for conduct under these procurement restrictions, preserving only judicial‑review and constitutional remedies.

Who Benefits and Who Bears the Cost

Every bill creates winners and losers. Here's who stands to gain and who bears the cost.

Who Benefits

  • Provincial government — gains flexible executive tools (orders, LGIC regulations, SEZ designations) to steer large projects, stabilize 'strategic' supply chains and accelerate approvals without typical procedural delays.
  • Designated mining and infrastructure proponents — receive access to permitting delivery teams, integrated authorization plans and a faster, more centralized approvals path if designated, which shortens timeline risk and bureaucratic friction.
  • Domestic suppliers and producers — stand to gain preference where origin‑based procurement rules exclude foreign suppliers, creating targeted market advantage for Ontario or Canadian vendors.
  • Trusted proponents and projects in Special Economic Zones — can obtain regulatory exemptions from provincial Acts and municipal by‑laws, reducing regulatory burdens for development within designated zones.
  • Energy system planners (IESO/OPG) — obtain explicit statutory authority to be directed on procurement origin and to implement government supply‑security priorities.

Who Bears the Cost

  • Foreign suppliers and firms with foreign beneficial ownership — may be excluded from provincially regulated procurements and face lost commercial opportunities where origin restrictions apply.
  • Municipal governments and local planners — risk diminished control where SEZ regulations exempt trusted proponents or projects from municipal by‑laws and local instruments.
  • Indigenous communities and conservation organizations — face heightened implementation and reputational risk because the bill centralizes discretion, reduces automatic protections on listing, and contemplates delegating procedural aspects of consultations to proponents in expedited permitting.
  • Private litigants, counsel and claimants — the extinguishment clauses remove many common legal avenues (tort, contract, injunctions) for challenging procurement, permitting and SEZ decisions, narrowing remedies to judicial review or constitutional claims and shifting litigation strategies.
  • Regulated entities and procurement officers — must implement origin determination rules (beneficial ownership tests, employee/location metrics) and rework processes on short notice, increasing compliance and transaction costs.

Key Issues

The Core Tension

The central dilemma is stark: use strong, discretionary government tools to speed strategic projects and protect critical supply chains, or preserve statutory procedures, judicial remedies and local controls that slow projects but provide transparency, legal accountability and environmental safeguards. The bill chooses the former; the trade‑offs are speed and supply‑chain control versus public process, local autonomy and the range of private legal remedies.

The bill sets up an enduring trade‑off: it replaces predictable, statute‑driven processes and remedies with discretionary executive mechanisms designed to speed projects and assert provincial control over supply chains. That design reduces transactional friction for designated projects and enables procurement preferences by origin, but it simultaneously concentrates decision‑making power in ministers and cabinet and narrows judicial recourse for affected third parties.

On implementation, several serious questions remain. The 'origin' tests are permissive and will be fleshed out by regulation (factors include residence, head office, incorporation, employee distribution, governing law and business activity), but those multi‑factor tests are blunt tools for complex multi‑jurisdictional supply chains and will invite compliance disputes.

The extinguishment provisions, while preserving judicial review, bar most other remedies — that shifts the litigation battlefield (and likely cost structures) toward administrative law and constitutional litigation and could produce novel Charter and procedural fairness claims. Finally, delegation of consultation tasks to proponents in the delivery‑team model risks procedural shortcuts in duty‑to‑consult workstreams; the bill leaves open how consultation outcomes will be recorded and reviewed.